PreBid Date:   12/05/2023 10:30 AM CST
PreBid Info:   Prebid Meeting: A Prebid meeting for all bidders will be held at Lincoln Public Schools Operations/Facilities and Maintenance Office, 800 South 24th Street, Lincoln, Nebraska on Tuesday, December 5, 2023, at 10:30 a.m. CST. Prospective prime bidders and major subcontractors are requested to attend.

Company:   Sinclair Hille & Architects
Bid Date:   12/14/2023 2:00 PM CST
Bid Info:   Owner will receive sealed lump sum bids until 2:00 p.m. on December 14, 2023.

Project Location: Lincoln, NE

Public Notes:
In general, Work includes a new, slab on grade 3,060 sf building addition on the northeast side of the existing school building. The exterior finish of tan brick with bands of red brick to match the existing school building will be installed. A skylight canopy will be installed over the new secondary north entrance to the building. Roofing material for the new addition will be a SBS Modified Bituminous Roofing membrane. Structure for the addition is to be concrete masonry unit (CMU) bearing walls supporting steel bar joists and metal deck. Exterior walls and interior corridor walls will be CMU construction. The roof will be framed with steel bar joists supporting the metal deck. Mechanically, new heat pumps will serve the addition with low return air in each classroom. The new additions will tie into the existing heat pump piping system. The existing geothermal wellfield will be utilized and does not require expansion for this project. New LED light fixtures and lighting controls including occupancy sensors, dimmers, and photocells will be provided per energy code. The school will be occupied by students during construction.



Job Purchase Information:
Bid Documents may be obtained from A&D Technical Supply, plans.adtechsupply.com (1822 N Street, Lincoln, NE. 68508, Phone 402-474-5454)

The complete digital set of bid documents are available for a non-refundable fee of $25.00 paid to A&D Technical Supply.

Printed sets of bid documents obtained upon submission of refundable deposit of $100.00 made payable to Lincoln Public Schools.

If required, documents can be mailed UPS for an additional payment of $25.00 paid to A&D Technical Supply.

Use the place order link in the top right to order bid documents.

Questions about obtaining bid documents should be directed to A&D Technical Supply at 402-474-5454 or planroom@ad4lincoln.com


Addenda