Contact:
|
Sheryl Lustgraaf
|
|
PreBid Date:
|
07/25/2012
10:00 AM CST
|
|
PreBid Info:
|
The Mandatory Pre-Bid Walk-Through will be held at the site on July 25, 2012 at 10:00 A.M.
|
|
|
Company:
|
Alvine and Associates Inc.
|
|
Bid Date:
|
08/02/2012
02:00 PM CST
|
|
Bid Info:
|
|
|
|
Project Location:
|
Omaha, Nebraska
|
|
|
|
|
|
|
|
Public Notes:
|
|
Sealed proposals for furnishing all plant, equipment, transportation, tools, materials, labor and skills necessary and incidental to perform all work described in the Proposed Contract Documents entitled:
Omaha State Office Building Life Safety Upgrades 2012
will be received at the State of Nebraska, State Office Building, located in Omaha, Nebraska until 2:00 P.M. on (date) and will then be publicly opened and read aloud.
|
|
Job Purchase Information:
|
Plans and specifications may be examined at the office of the Engineer, Alvine Engineering in Omaha or Lincoln, 1102 Douglas on the Mall, Omaha, Nebraska 68102 or 1800 O Street, Suite 104, Lincoln, Nebraska; Lincoln Builder’s Bureau, Lincoln, Nebraska; Omaha Builders Exchange, Omaha, NE.
The said Documents have been prepared by Alvine Engineering, and may be obtained from A&D Technical Supply, at 4320 S 89th Street, Omaha, Nebraska 68127 with a deposit in the amount of $50.00 made payable to Alvine Engineering and left with A&D Technical Supply - Omaha at the time of document pick-up.
The deposit will be returned to the contractor / subcontractor upon return of the plans, specification and addenda in good condition within thirty (30) days after the bid opening date. Plans are to be returned to A&D Technical Supply, Omaha, Nebraska.
If shipping is required there is a non refundable flat rate of $20.00 per set made payable to A&D Technical Supply. There will be a $8.00 handling fee for the use of shipper numbers (UPS).
|
|
Addenda- 07/27/2012 - Addendum #1 Addendum #1 was posted on 7/27/2012 and distributed by Alvine Engineering. Click to View
- 07/31/2012 - Addendum #2 Addendum #2 was posted on 7/31/2012 and distributed by Alvine Engineering. Click to View
- 07/31/2012 - Addendum #3 Addendum #3 was posted on 7/31/2012 and distributed by Alvine Engineering. Click to View
|
|
|
|