Contact:
|
Andrea Yeoman
|
|
PreBid Date:
|
Not furnished
|
|
PreBid Info:
|
|
|
|
Company:
|
Snyder & Associates, Inc. - Council Bluffs
|
|
Bid Date:
|
04/26/2016
10:00 AM CST
|
|
Bid Info:
|
Sealed bids will be received in the 209 Pearl Street office of the City Clerk until 10:00 o'clock a.m. on April 26, 2016 for all work set forth in the plans, specifications, and proposals for the above mentioned project. Bids will be opened and publicly read immediately following the filing deadline in the City Clerk's office of City Hall.
|
|
|
Project Location:
|
Council Bluffs, Nebraska
|
|
|
|
|
|
|
|
Public Notes:
|
|
MAJOR ITEMS OF WORK for this project include the following approximate quantities: 4,146 SY Street Pavement Removal; 3,700 SY Asphalt Milling; 4,560 SY 6" Granular Subbase; 4,005 SY 7" Non-Reinforced PCC Pavement with 6" Integral Curb; 312 SY 7" Non-Reinforced PCC Pavement with 1.5' Wall and Curb; 360 SY 4" PCC Sidewalk; 1,410 LF 15" RCP Storm Sewer, Class III; 12 EA Single Grate Intake, Type SW-501; 1,582 LF 8" PVC Sanitary Sewer; 7 EA Sanitary Manholes, Type SW-301; 1,430 LF of 8" DI Water Main; 300 LF of 6" DI Water Main and Appurtenances.
|
|
Job Purchase Information:
|
Contract documents, including construction drawings, are placed in the Office of the City Clerk for examination.
Copies for bidding may be obtained from A&D Technical Supply Company, 4320 South 89th Street, Omaha, NE 68127, or at www.adtechsupply.com (ONE SET PER PLAN HOLDER). There is no deposit on this project.
If shipping is required, there is a flat rate of $25.00 per set (Please address all checks for shipping to A&D Tech Supply Plan Room).CD's and Downloads containing a full set of Bid Documents in PDF format are available upon receipt of a non-refundable fee in the amount of $20.00 payable to A&D Technical Supply Co., Inc.
Shipping checks are to mailed to A&D Technical Supply Company, 4320 S. 89th Street, Omaha, Ne 68127.
Planholders shall return contract documents in a reusable condition to A&D Technical Supply Company Inc., within 14 calendar days from the City Council award of the project.
|
|
Addenda- 04/22/2016 - Addendum #1 Addendum #1 was faxed on 4-22-2016 Click to View
|
|
|
|