Contact:
|
Chris Koenig
|
|
PreBid Date:
|
08/18/2015
02:00 PM CST
|
|
PreBid Info:
|
A prebid conference will be held at 2:00 PM on August 18, 2015 at the Project Site. Bidders are encouraged to attend and participate in the conference.
|
|
|
Company:
|
HDR Engineering Inc. - Omaha
|
|
Bid Date:
|
08/27/2015
10:00 AM CST
|
|
Bid Info:
|
Sealed bids will be received in the 209 Pearl Street office of the City Clerk until 10:00 o'clock a.m. on August 27, 2015 for all work set forth in the plans, specifications, and proposals for the above mentioned project. Bids will be opened and publicly read immediately following the filing deadline in the City Clerk's office of City Hall.
|
|
|
Project Location:
|
Council Bluffs, Iowa
|
|
|
|
|
|
|
|
Public Notes:
|
|
MAJOR ITEMS OF WORK for this project include the following approximate quantities: Subgrade preparation, storm sewers, water mains, electrical, paving, streetscape amenities, and landscaping.
|
|
Job Purchase Information:
|
Bid Documents may be obtained from the office of A&D Technical Supply Co., Inc., 4320 S. 89th Street, Omaha, NE 68127, (402)592-4950 upon receipt of a refundable deposit in the amount of $100.00 payable to HDR Engineering, Inc. *A Builder's Card will NOT be accepted in lieu of deposit check.
CD's and Downloads containing a full set of Bid Documents in PDF format are available upon receipt of a non-refundable fee in the amount of $25.00 payable to A&D Technical Supply Co., Inc. Only complete sets of Bid Documents may be obtained.
If shipping of Bid Documents is required, there is a non-refundable fee in the amount of $30.00 payable to A&D Technical Supply Co., Inc. If shipping of CD is required, there is a flat fee in the amount of $9.00 payable to A&D Technical Supply Co., Inc.
Bid Documents MUST be returned, in good condition, within 14 calendar days from the City Council Award of the project to obtain a deposit refund. If Bid Documents are NOT returned within the time specified, the deposit check will be forfeited.
|
|
Addenda- 08/14/2015 - Addendum #1 Addendum #1 was posted & mailed on 08/14/2015 Click to View
- 08/20/2015 - Addendum #2 Addendum #2 was mailed on 08/20/2015 Click to View
- 08/25/2015 - Addendum #3 Addendum #3 was faxed on 8-25-2015 Click to View
|
|
|
|