KPS - Horizon Middle School - Additions and Renovation

BD Construction, Inc. is acting as the CM - Agent for this project.
           Place Order 

 

    

Contact:   Jacob Sertich
PreBid Date:   02/17/2015 03:30 PM
PreBid Info:   A Pre-Bid Conference will be held at 3:30 PM on February 17, 2015 at Horizon Middle School - Media Center (Library), 915 West 35th Street, Kearney, Nebraska 68845.

Meeting attendance is strongly recommended for major subcontractors.

Company:   Wilkins Architecture Design Planning
Bid Date:   04/08/2015 02:30 PM CST
Bid Info:   Bids signed and under seal, executed, dated and submitted for the furnishing of Foundation, Site Work, Bulk Steel and Site Utilities (Bid Packages 1, 2, 3 & 39) for the Kearney Public Schools - Horizon Middle School Additions and Renovation prior to 2:30 PM on April 8, 2015 at the Office of the Finance Director located within the Whittier Learning Resource Center, 310 West 24th Street, Kearney, Nebraska. Use north entrance.

Bids signed and under seal, executed, dated and submitted for the furnishing of all labor, materials and equipment for the Kearney Public Schools - Horizon Middle School Additions and Renovation that was not included in the February 24th Bid prior to 2:30 PM on March 4, 2015 at the Office of the Finance Director located within the Whittier Learning Resource Center, 310 West 24th Street, Kearney, Nebraska. Use north entrance.

Project Location: Kearney, Nebraska

Public Notes:
Work of this proposed Contract comprises remodeling, renovation, and demolition, including general construction, structural, mechanical and electrical Work.

Project Address: 915 West 35th Street, Kearney, Nebraska.

Construction Manager - Agent's Name: BD Construction, Inc.

The Work consists of two, new, one-story, slab-on-grade building additions totaling 7,708 SF and renovation of the existing, one-story, slab-on-grade building mostly constructed in 1968 and encompassing 104,663 SF. The site consists of earthwork, utilities and limited concrete paving. The building additions consist of load-bearing masonry construction with brick veneer, precase hollow-core roof deck, aluminum storefront, interior metal stud framing with gypsum wallboard, wood interior doors with hollow metal frames. Finishes include paint, rubber flooring, carpet flooring and acoustical panel and gypsum wallboard ceilings. Wholesale renovation work encompasses approximately 42,463 SF of the existing building and includes complete demolition of interior walls, operable partition walls, floor/ceiling finishes, mechanical, electrical and plumbing and preparation for new aluminum storefront, interior metal stud framing with gypsum wallboard, wood interior doors with hollow metal frames. Finishes include paint, rubber flooring, carpet flooring and acoustical panel and gypsum wallboard ceilings. Included in the Work is mechanical, electrical and plumbing throughout the entire building including the installation of a fire sprinkler system.

Contract Type: Multiple Trade contracts based on a Stipulated Price as described in Document 00 5200 - Agreement Form.

Project will be constructed under multiple trade contracts with one Construction Manager - Agent coordinating and overseeing all of the project on behalf of the Owner.

Each trade contractor will secure and pay for permits and governmental fees, licenses and inspections necessary for proper execution and completion of the Prime Contractor's Work. The building permit itself for the entire project will be secured and paid for by the Owner or the Owner's Agent.



Job Purchase Information:
Bid Documents may be obtained from the office of A&D Technical Supply Co., Inc, 4320 S. 89th Street, Omaha, NE 68127 (402)592-4950 upon receipt of a refundable deposit in the amount of $200.00 payable to Wilkins Hinrichs Stober Architects. *A Builder's Card will NOT be accepted in lieu of deposit check.

CD's containing a full set of Bid Documents in PDF format are available upon receipt of a non-refundable fee in the amount of $40.00 payable to A&D Technical Supply Co., Inc.
Only complete sets of Bid Documents may be obtained. - No partial set orders will be issued.

If shipping of Bid Documents is required, there is a non-refundable fee in the amount of $50.00 payable to A&D Technical Supply Co., Inc.
If shipping of CD is required, there is a flat fee in the amount of $9.00 payable to A&D Technical Supply Co., Inc.

ALL BID DOCUMENTS SHALL BE RETURNED TO THE OFFICE OF THE ARCHITECT, WILKINS HINRICHS STOBER ARCHITECTS, 2908 West 39th Street, Suite A, Kearney, NE 68845 within 15 calendar days of Bid Opening to obtain a deposit refund.
If Bid Documents are NOT returned within stipulated time period, deposit will be forfeited.


Addenda
  • 02/17/2015 - Bid Bulletin #1 Bid Bulletin #1 was mailed on 02/13/2015  Click to View
  • 02/20/2015 - Bid Bulletin #2 Bid Bulletin #2 will be mailed on 2-20-2015  Click to View
  • 02/25/2015 - Bid Bulletin #3 Revised Bid Bulletin #3 was posted & mailed on 02/25/2015  Click to View
  • 02/26/2015 - Bid Bulletin #4 Bid Bulletin #4 was faxed on 2-26-2015  Click to View
  • 03/02/2015 - Bid Bulletin #5 Bid Bulletin #5 was faxed on 03/02/2015  Click to View
  • 03/20/2015 - Bid Bulletin #6 Bid Bulletin #6 was faxed on 03/20/2015  Click to View